Timeline

Planning application and construction

It is anticipated that the earliest construction of the first phase of the wider site would start in late 2023, subject to approval of Reserved Matters applications, which will provide details of the layout and house types.

Development is likely to take up to 10 years to construct, potentially being completed by 2034.

A timeline for the application and anticipated construction is provided below.

Key Delivery Milestones Estimated Dates
Work begins on the core site October 2020
Preparation of the Outline Planning Application for the wider site Ongoing
Local Plan Examination hearings January and February 2021
Public consultation 21 June to 11 July 2021
Submission of Outline Planning Application for the wider site Late summer / early autumn 2021
Potential Determination of Outline Planning Application for the wider site Spring 2022
Submission of Reserved Matters planning application (appearance, scale, layout, landscaping) Late 2022
Potential determination of Reserved Matters planning application for phase 1 of wider site Spring 2023
Start on site  Late 2023
Anticipated primary school opening September 2025
Completion of Lea Castle Village 2034